Agile Docs maintains a number of fields on each Epic which are available for use in Jira.
To expose these fields, go to Project Settings => Apps => App Fields and turn on Agile Docs - Estimate Tree for Jira.
You’ll then have access to the following numerical fields in Jira on each Epic:
Field | Value |
---|---|
| Story point total of Epic |
| Story points completed in Epic |
| Story point % progress of Epic |
| Total time spent in Epic |
| Total current estimate of Epic. This corresponds to the total time spent + time remaining of the Epic |
| The total original estimate of an Epic |
| Time % progress of Epic. This corresponds to the time spent / current estimate of the Epic |
Once enabled, these fields can be configured to display inside each Epic:
You can also use these fields in JQL queries.
For example, to find every Epic with more than 40 story points completed, you could create a filter using the expression “Story Points Completed” > 40. You could also set the fields “Story Points Completed”, “Story Point Total” and “Story Point Progress” to display in your filter.