Sub-Task Estimates Aren't Rolling Up To Parent Issues

Ensure there’s no estimates on your parent issues. Agile Docs looks for an estimate on each issue. If it finds one, it uses that estimate. If no estimate is found, it looks for estimates on it’s children. The estimates of the child issues are then rolled up to the parent. To roll up estimates from sub-tasks, leave the story point estimate of the parent issue blank. Or if using time tracking, set the original estimate and remaining estimate on the parent issue to 0.